Instead of discussing the naval buildup in the thread about the army build up a separate thread may be sensible.
The buildup of the navy hinges on many assumptions so i try to make sensible ones. Slider rushing can make sense, but itis complicated so i take it out of the equation. I assume Germany starts 1936 with a move hawk lobby followed by a move free markets in 1937 and 3 moves professional army for cheaper upgrading in 1938, 1939 and 1940. Also i assume that Militaristic Focus gives -5% on upgrading and that retooling is 72 days.
I assume that unlike assembly line experimentation the proper assembly line tech donnot apply for a navy that is to be completed at 1940/4/30. That is the day the NAP with soviet union expiries and it is near the time when new naval bases in the west are taken.
I present a few possible naval buildups. They are supposed to be economically sensible and that implies that all brigades are built separately from the ships. This saves retooling and supply costs and it enables to minimize ic spend on the navy before Danzig.
570 days before 1940/4/30 is 1938/9/30. That is Munich when full hawk lobby will be achieved. Before that -20% from sliders apply, after it it will be -24%. So most construction will occur after it.
Supply consumption starts once retooling is done. That is one reason why i will not maximize gearing bonus on the brigades, the other reason is that i like to avoid that brigades have no ships to be attached to.
When saving the game total progress is saved only 4 digits far. This can lead to the effect that total progress is only 0.9999 when it should be complete.
0.) 2 lines of DD1938 cost a total of 8.36 ic. Retooling starts 452 days before 1940/4/30 at 1939/1/28. But the first 36 days only at 7.6 for DD1936. At 1939/3/4 the 2 lines are upgraded. At 1939/5/10 construction starts. 2 units each are completed at 1939/9/23, at 1940/1/30 and at 1940/4/30.
2 lines of ASW1937 cost a total of 2.28 ic. Retooling starts 222 days before 1940/4/30 at 1939/9/18. Construction starts at 1939/10/24. 2 units each are completed at 1939/12/29, 1940/3/1 and 1940/4/30. Upgrading to ASW1940 costs further 127.68 icd. So it is 574.56 icd of retooling, 3176.8 icd of construction and a total of 3879.04 icd for the screens for one fleet of surface ships.
1.) 6 lines of CV1938 cost a total of 31.92 ic. Retooling starts 627 days before 1940/4/29 at 1938/8/2. The first 36 days of retooling still cost 28.8 ic for CV1936. At 1939/9/8 the upgrading to CV1938 increases it to 33.6 ic. At 1939/9/30 it reduces to 31.92. At 1939/10/14 construction starts. 555 days later at 1940/4/29 the 6 units are ready.
6 lines of CAG1938 cost a total 45.6 ic. Retooling starts 158 days before 1940/4/30 at 1939/11/22, but the first 18 days only at 36.48 ic for CAG1936. At 1939/12/10 the upgrading to CAG1938 occurs. At 1939/12/28 construction starts. At 1940/4/30 the 6 brigades can be attached to the carriers. Upgrading to CAG1940 costs further 1773.41 icd. So it is 3700.32 icd of retooling, 23278.8 icd of construction and a total of 28752.53 icd for the capitals for one CFT. The entire CTF costs 32631.57 icd.
6 CV1938-CAG1941 + 6 DD1938-ASW1940 have a firing range of 185 km and a see attack of 6x10x0.8 = 48. Total convoy attack is 6x10+6x4 = 84.
2.) 6 lines of SHBB1938 cost a total of 52.44 ic. Retooling starts 467 days before 1940/4/29 at 1939/1/12. Construction starts at 1939/3/24, the 6 units are complete at 1940/4/29.
6 lines of capital ship AA1938 cost 4.56 ic. Retooling starts 101 days before 1940/4/30 at 1940/1/29. Construction starts at 1940/3/5, the 6 units are complete at 1940/4/30.
6 lines of capital ship Radar 1937 costs 4.56 ic. Retooling starts 116 days before 1940/4/30 at 1940/1/14. Construction starts at 1940/2/20, the 6 units are complete at 1940/4/30. Upgrading to RA1940 costs further 131.96 icd.
6 lines of capital ship Fire Control 1938 cost 9.12 ic. Retooling starts 97 days before 1940/4/30 at 1940/1/23. Construction starts at 1940/2/29, the 6 units are complete at 1940/4/30. Upgrading to FX1940 costs further 149.55 icd.
6 lines of secondary armament 1936 cost 2.28 ic. Retooling starts 131 days before 1940/4/30 at 1939/12/29. Construction starts at 1940/2/5, the 6 units are complete at 1940/4/30.
6 lines of capital ship spotters 1936 cost 4.56 ic. Retooling starts 131 days before 1940/4/30 at 1939/12/29. Construction starts at 1940/2/5, the 6 units are complete at 1940/4/30.
It is 4675.68 icd of retooling, 22581.12 icd of construction and a total of 27538.31 icd for the capitals for one SAG. The entire SAG costs 31417.35 icd. With only 4 SHBB1938 it is only 22237.92 icd.
6 brigaded SHBB1938 + 6 DD1938-ASW1940 have a firing range of 48 km and a see attack of 6x29x0.8 = 139.2. Total convoy attack is 6x28+6x4 = 192.
4 brigaded SHBB1938 + 6 DD1938-ASW1940 have a firing range of 48 km and a see attack of 4x29x0.84 = 97.44. Total convoy attack is 4x28+6x4 = 136.
3.) 6 lines of BB1936 cost 36.48 ic, but only 31.92 ic for the first 36 days as BB1930. Retooling starts 460 days before 1940/4/29 at 1939/1/19. Construction starts at 1939/4/1, the 6 units are complete at 1940/4/29.
The 5 brigades are the same as for SHBB1938. So it is 3365.28 icd of retooling, 16021.56 icd of construction and a total of 19668.35 icd for the capitals for one SAG. The entire SAG costs 23547.39 icd.
6 brigaded BB1936 + 6 DD1938-ASW1940 have a firing range of 46 km and a see attack of 6x24x0.8 = 115.2. Total convoy attack is 6x23+6x4 = 162.
4.) 3 lines of BC1938 costs 13.68 ic and 14.4 ic before 1938/9/30, but only 13.2 ic for the first 36 days as BC1936. Retooling starts 728 days before 1940/4/30 at 1938/4/22. Construction starts at 1938/7/8, the first 3 units are complete at 1939/6/12, the second 3 units at 1940/4/30.
3 lines of capital ship AA1938 cost 2.28 ic. Retooling starts 163 days before 1940/4/30 at 1939/11/17. Construction starts at 1939/12/23, the first 3 units are complete at 1940/2/28, the second 3 units at 1940/4/30.
3 lines of capital ship Radar 1937 costs 2.28 ic. Retooling starts 192 days before 1940/4/30 at 1939/10/18. Construction starts at 1939/11/24, the first 3 units are complete at 1940/2/14, the second 3 units at 1940/4/30. Upgrading to RA1940 costs further 131.96 icd.
3 lines of capital ship Fire Control 1938 cost 4.56 ic. Retooling starts 155 days before 1940/4/30 at 1939/11/25. Construction starts at 1940/1/1, the first 3 units are complete at 1940/3/2, the second 3 units at 1940/4/30. Upgrading to FX1940 costs further 149.55 icd.
3 lines of capital ship spotters 1936 cost 2.28 ic. Retooling starts 222 days before 1940/4/30 at 1939/9/18. Construction starts at 1939/10/24, the first 3 units are complete at 1940/1/29, the second 3 units at 1940/4/30.
It is 1404 icd of retooling, 10647.96 icd of construction and a total of 12333.47 icd for the capitals for one SAG. The entire SAG costs 16212.51 icd.
6 brigaded BC1938 + 6 DD1938-ASW1940 have a firing range of 44 km and a see attack of 6x17x0.8 = 81.6. Total convoy attack is 6x16+6x4 = 120.
5.) 30 lines of HSS1933 cost 102.6 ic. Retooling starts 546 days before 1940/4/30 at 1938/10/24. Construction starts at 1939/1/6, the first 30 units are complete at 1939/9/9, the second 30 units at 1940/4/30.
It is 7387.2 icd of retooling, 48632.4 icd of construction and a total of 56019.6 icd for the 10 wolfspacks of size 6.
12 unbrigaded HSS1933 have a firing range of 16 km and a see attack of 12x6x0.8 = 57.6. Total convoy attack of 60 unbrigaded HSS1933 is 60x10 = 600.
6.) 15 lines of SS1938 cost 34.2 ic, but only 22.8 ic for the first 36 days as SS1930. Retooling starts 524 days before 1940/4/30 at 1938/11/16. Construction starts at 1939/1/28, 15 units each are completed at 1939/5/30, at 1939/9/28, at 1940/1/16 and at 1940/4/30.
It is 2052 icd of retooling, 15458.4 icd of construction and a total of 17510.4 icd for the 10 wolfspacks of size 6.
12 unbrigaded SS1938 have a firing range of 18 km and a see attack of 12x4x0.8 = 38.4. Total convoy attack of 60 unbrigaded SS1938 is 60x7 = 420.
7.) 15 lines of SS1930 cost 22.8 ic. Retooling starts 524 days before 1940/4/30 at 1938/11/16. Construction starts at 1939/1/28, 15 units each are completed at 1939/5/30, at 1939/9/28, at 1940/1/16 and at 1940/4/30.
It is 1641.6 icd of retooling, 10305.6 icd of construction and a total of 11947.2 icd for the 10 wolfspacks of size 6.
12 unbrigaded SS1930 have a firing range of 17 km and a see attack of 12x4x0.8 = 38.4. Total convoy attack of 60 unbrigaded SS1930 is 60x6 = 360.
I consider it practical to compare figures to a 2 year period of 720 days.
1. The 32631.57 icd for CTF equal 45.32 ic over 720 days.
2. The 31417.35 icd for the heavy SAG equal 43.64 ic over 720 days.
3. The 23547.39 icd for the Bismarck SAG equal 32.70 ic over 720 days.
4. The 16212.51 icd for the Scharnhorst SAG equal 22.52 ic over 720 days.
5. The 56019.6 icd for 10 heavy wolfpacks equal 77.81 ic over 720 days.
6. The 17510.4 icd for 10 1938 wolfspacks equal 24.32 ic over 720 days.
7. The 11947.2 icd for 10 1930 wolfpacks equal 16.59 ic over 720 days.
Similar is true about maintenance costs over 720 days. Manpower is less relevant for the navy, so i just use the supply consumption during rest and construction at an assumed 4 supplies/icd.
5. HSS1933 consume 1.4 supplies, over 720 days that equals 252 icd or 30.32 % of construction icd.
6. SS1938 consume 0.6 supplies, over 720 days that equals 108 icd or 38.83 % of construction icd.
7. SS1930 consume 0.5 supplies, over 720 days that equals 90 icd or 48.53 % of construction icd.
The buildup of the navy hinges on many assumptions so i try to make sensible ones. Slider rushing can make sense, but itis complicated so i take it out of the equation. I assume Germany starts 1936 with a move hawk lobby followed by a move free markets in 1937 and 3 moves professional army for cheaper upgrading in 1938, 1939 and 1940. Also i assume that Militaristic Focus gives -5% on upgrading and that retooling is 72 days.
I assume that unlike assembly line experimentation the proper assembly line tech donnot apply for a navy that is to be completed at 1940/4/30. That is the day the NAP with soviet union expiries and it is near the time when new naval bases in the west are taken.
I present a few possible naval buildups. They are supposed to be economically sensible and that implies that all brigades are built separately from the ships. This saves retooling and supply costs and it enables to minimize ic spend on the navy before Danzig.
570 days before 1940/4/30 is 1938/9/30. That is Munich when full hawk lobby will be achieved. Before that -20% from sliders apply, after it it will be -24%. So most construction will occur after it.
Supply consumption starts once retooling is done. That is one reason why i will not maximize gearing bonus on the brigades, the other reason is that i like to avoid that brigades have no ships to be attached to.
When saving the game total progress is saved only 4 digits far. This can lead to the effect that total progress is only 0.9999 when it should be complete.
0.) 2 lines of DD1938 cost a total of 8.36 ic. Retooling starts 452 days before 1940/4/30 at 1939/1/28. But the first 36 days only at 7.6 for DD1936. At 1939/3/4 the 2 lines are upgraded. At 1939/5/10 construction starts. 2 units each are completed at 1939/9/23, at 1940/1/30 and at 1940/4/30.
2 lines of ASW1937 cost a total of 2.28 ic. Retooling starts 222 days before 1940/4/30 at 1939/9/18. Construction starts at 1939/10/24. 2 units each are completed at 1939/12/29, 1940/3/1 and 1940/4/30. Upgrading to ASW1940 costs further 127.68 icd. So it is 574.56 icd of retooling, 3176.8 icd of construction and a total of 3879.04 icd for the screens for one fleet of surface ships.
1.) 6 lines of CV1938 cost a total of 31.92 ic. Retooling starts 627 days before 1940/4/29 at 1938/8/2. The first 36 days of retooling still cost 28.8 ic for CV1936. At 1939/9/8 the upgrading to CV1938 increases it to 33.6 ic. At 1939/9/30 it reduces to 31.92. At 1939/10/14 construction starts. 555 days later at 1940/4/29 the 6 units are ready.
6 lines of CAG1938 cost a total 45.6 ic. Retooling starts 158 days before 1940/4/30 at 1939/11/22, but the first 18 days only at 36.48 ic for CAG1936. At 1939/12/10 the upgrading to CAG1938 occurs. At 1939/12/28 construction starts. At 1940/4/30 the 6 brigades can be attached to the carriers. Upgrading to CAG1940 costs further 1773.41 icd. So it is 3700.32 icd of retooling, 23278.8 icd of construction and a total of 28752.53 icd for the capitals for one CFT. The entire CTF costs 32631.57 icd.
6 CV1938-CAG1941 + 6 DD1938-ASW1940 have a firing range of 185 km and a see attack of 6x10x0.8 = 48. Total convoy attack is 6x10+6x4 = 84.
2.) 6 lines of SHBB1938 cost a total of 52.44 ic. Retooling starts 467 days before 1940/4/29 at 1939/1/12. Construction starts at 1939/3/24, the 6 units are complete at 1940/4/29.
6 lines of capital ship AA1938 cost 4.56 ic. Retooling starts 101 days before 1940/4/30 at 1940/1/29. Construction starts at 1940/3/5, the 6 units are complete at 1940/4/30.
6 lines of capital ship Radar 1937 costs 4.56 ic. Retooling starts 116 days before 1940/4/30 at 1940/1/14. Construction starts at 1940/2/20, the 6 units are complete at 1940/4/30. Upgrading to RA1940 costs further 131.96 icd.
6 lines of capital ship Fire Control 1938 cost 9.12 ic. Retooling starts 97 days before 1940/4/30 at 1940/1/23. Construction starts at 1940/2/29, the 6 units are complete at 1940/4/30. Upgrading to FX1940 costs further 149.55 icd.
6 lines of secondary armament 1936 cost 2.28 ic. Retooling starts 131 days before 1940/4/30 at 1939/12/29. Construction starts at 1940/2/5, the 6 units are complete at 1940/4/30.
6 lines of capital ship spotters 1936 cost 4.56 ic. Retooling starts 131 days before 1940/4/30 at 1939/12/29. Construction starts at 1940/2/5, the 6 units are complete at 1940/4/30.
It is 4675.68 icd of retooling, 22581.12 icd of construction and a total of 27538.31 icd for the capitals for one SAG. The entire SAG costs 31417.35 icd. With only 4 SHBB1938 it is only 22237.92 icd.
6 brigaded SHBB1938 + 6 DD1938-ASW1940 have a firing range of 48 km and a see attack of 6x29x0.8 = 139.2. Total convoy attack is 6x28+6x4 = 192.
4 brigaded SHBB1938 + 6 DD1938-ASW1940 have a firing range of 48 km and a see attack of 4x29x0.84 = 97.44. Total convoy attack is 4x28+6x4 = 136.
3.) 6 lines of BB1936 cost 36.48 ic, but only 31.92 ic for the first 36 days as BB1930. Retooling starts 460 days before 1940/4/29 at 1939/1/19. Construction starts at 1939/4/1, the 6 units are complete at 1940/4/29.
The 5 brigades are the same as for SHBB1938. So it is 3365.28 icd of retooling, 16021.56 icd of construction and a total of 19668.35 icd for the capitals for one SAG. The entire SAG costs 23547.39 icd.
6 brigaded BB1936 + 6 DD1938-ASW1940 have a firing range of 46 km and a see attack of 6x24x0.8 = 115.2. Total convoy attack is 6x23+6x4 = 162.
4.) 3 lines of BC1938 costs 13.68 ic and 14.4 ic before 1938/9/30, but only 13.2 ic for the first 36 days as BC1936. Retooling starts 728 days before 1940/4/30 at 1938/4/22. Construction starts at 1938/7/8, the first 3 units are complete at 1939/6/12, the second 3 units at 1940/4/30.
3 lines of capital ship AA1938 cost 2.28 ic. Retooling starts 163 days before 1940/4/30 at 1939/11/17. Construction starts at 1939/12/23, the first 3 units are complete at 1940/2/28, the second 3 units at 1940/4/30.
3 lines of capital ship Radar 1937 costs 2.28 ic. Retooling starts 192 days before 1940/4/30 at 1939/10/18. Construction starts at 1939/11/24, the first 3 units are complete at 1940/2/14, the second 3 units at 1940/4/30. Upgrading to RA1940 costs further 131.96 icd.
3 lines of capital ship Fire Control 1938 cost 4.56 ic. Retooling starts 155 days before 1940/4/30 at 1939/11/25. Construction starts at 1940/1/1, the first 3 units are complete at 1940/3/2, the second 3 units at 1940/4/30. Upgrading to FX1940 costs further 149.55 icd.
3 lines of capital ship spotters 1936 cost 2.28 ic. Retooling starts 222 days before 1940/4/30 at 1939/9/18. Construction starts at 1939/10/24, the first 3 units are complete at 1940/1/29, the second 3 units at 1940/4/30.
It is 1404 icd of retooling, 10647.96 icd of construction and a total of 12333.47 icd for the capitals for one SAG. The entire SAG costs 16212.51 icd.
6 brigaded BC1938 + 6 DD1938-ASW1940 have a firing range of 44 km and a see attack of 6x17x0.8 = 81.6. Total convoy attack is 6x16+6x4 = 120.
5.) 30 lines of HSS1933 cost 102.6 ic. Retooling starts 546 days before 1940/4/30 at 1938/10/24. Construction starts at 1939/1/6, the first 30 units are complete at 1939/9/9, the second 30 units at 1940/4/30.
It is 7387.2 icd of retooling, 48632.4 icd of construction and a total of 56019.6 icd for the 10 wolfspacks of size 6.
12 unbrigaded HSS1933 have a firing range of 16 km and a see attack of 12x6x0.8 = 57.6. Total convoy attack of 60 unbrigaded HSS1933 is 60x10 = 600.
6.) 15 lines of SS1938 cost 34.2 ic, but only 22.8 ic for the first 36 days as SS1930. Retooling starts 524 days before 1940/4/30 at 1938/11/16. Construction starts at 1939/1/28, 15 units each are completed at 1939/5/30, at 1939/9/28, at 1940/1/16 and at 1940/4/30.
It is 2052 icd of retooling, 15458.4 icd of construction and a total of 17510.4 icd for the 10 wolfspacks of size 6.
12 unbrigaded SS1938 have a firing range of 18 km and a see attack of 12x4x0.8 = 38.4. Total convoy attack of 60 unbrigaded SS1938 is 60x7 = 420.
7.) 15 lines of SS1930 cost 22.8 ic. Retooling starts 524 days before 1940/4/30 at 1938/11/16. Construction starts at 1939/1/28, 15 units each are completed at 1939/5/30, at 1939/9/28, at 1940/1/16 and at 1940/4/30.
It is 1641.6 icd of retooling, 10305.6 icd of construction and a total of 11947.2 icd for the 10 wolfspacks of size 6.
12 unbrigaded SS1930 have a firing range of 17 km and a see attack of 12x4x0.8 = 38.4. Total convoy attack of 60 unbrigaded SS1930 is 60x6 = 360.
I consider it practical to compare figures to a 2 year period of 720 days.
1. The 32631.57 icd for CTF equal 45.32 ic over 720 days.
2. The 31417.35 icd for the heavy SAG equal 43.64 ic over 720 days.
3. The 23547.39 icd for the Bismarck SAG equal 32.70 ic over 720 days.
4. The 16212.51 icd for the Scharnhorst SAG equal 22.52 ic over 720 days.
5. The 56019.6 icd for 10 heavy wolfpacks equal 77.81 ic over 720 days.
6. The 17510.4 icd for 10 1938 wolfspacks equal 24.32 ic over 720 days.
7. The 11947.2 icd for 10 1930 wolfpacks equal 16.59 ic over 720 days.
Similar is true about maintenance costs over 720 days. Manpower is less relevant for the navy, so i just use the supply consumption during rest and construction at an assumed 4 supplies/icd.
5. HSS1933 consume 1.4 supplies, over 720 days that equals 252 icd or 30.32 % of construction icd.
6. SS1938 consume 0.6 supplies, over 720 days that equals 108 icd or 38.83 % of construction icd.
7. SS1930 consume 0.5 supplies, over 720 days that equals 90 icd or 48.53 % of construction icd.